Sustainability & Responsibility

left arrow

We are focusing on the UN’s #7 Sustainability Development Goal: Affordable and Clean Energy and we invite you to pledge your house to the cause.

left arrow

We support PMI’s 2022 Hours for Impact initiative where we have committed to assisting local organizations in executing their projects

Our team also volunteers to help organize events in their technical and personal circles, most recently the PMI’s 2022 Revelations Symposium.

We are always looking for additional causes to support, from river and lake cleanups to teaching and volunteer opportunities to many others.

Feel free to reach out at any time.

GHG Emissions

Saint Antonin HP Feasibility Study

Description de projet

Winston Hydro Inc., mandated Equinox Construction Services (ECS) to develop a Feasibility Study that would satisfy Hydro-Québec’s requirements. TAs owner of the Saint-Antonin dam, Winston Hydro wanted to refurbish the station and put it back into service with new turbines and generators, new automated water diversion equipment and various other rehabilitation measures.

ECS assessed and reviewed all the factors required to developed the station’s generation capacity through an Energy Model, the Financial Model, the Scheduling and Permitting requirements as well as the proposed Cost of the sold power.

ECS was successful in attracting Hydro-Québec’s attention and assisted the owner with negotiating a Power

Purchase Agreement, specific clauses and an in-service date based on Hydro-Québec’s in-house studies.    

CLIENT

Winston Hydro Inc.

LOCATION

Saint-Antonin, Québec.

DATE

January 2024 to March 2024

Team

COST

N/A

PROFESSIONAL FEES

16 000$

Services Provided

  • Hydrology review
  • Energy modeling with in-house as well as RETScreen models
  • Assessment of generation capacity
  • Tender process with turbine suppliers
  • Financial analysis
  • OPEX and CAPEX cost review
  • Scheduling and permitting requirements
  • Preparation of a Feasibility Study destined for Hydro-Québec
  • Negotiation for Power Purchase Agreement

Challenges

  • Developing a report according to Hydro-Québec’s requirements
  • Building a project that is financially and technically viable