Sustainability & Responsibility

left arrow

We are focusing on the UN’s #7 Sustainability Development Goal: Affordable and Clean Energy and we invite you to pledge your house to the cause.

left arrow

We support PMI’s 2022 Hours for Impact initiative where we have committed to assisting local organizations in executing their projects

Our team also volunteers to help organize events in their technical and personal circles, most recently the PMI’s 2022 Revelations Symposium.

We are always looking for additional causes to support, from river and lake cleanups to teaching and volunteer opportunities to many others.

Feel free to reach out at any time.

GHG Emissions

Norland HP – Debris & Safety Boom

Description de projet

Timber Run Hydropower Corporation mandated Equinox Construction Services (ECS) to carry out the design, contracting, sourcing, installation and commissioning of a combination debris/safety boom for the Norland Hydropower Plant. Various suppliers were contacted to provide pricing for the supply of the boom and design of the bank anchors. No in-water anchors were needed for this 22 m-long section.

ECS managed the supply, logistics, and delivery, as well as the installation of the new boom. The proper positioning, elevation, depth and arrangement of the boom were determined by ECS' engineering staff.

For this mandate, no drawings, bathymetry, detailed engineering work or consultations were required, given the relatively short length.

Furthermore, ECS managed the approval process with the Parcs Canada Agency (PCA) and remains on hand to carry out regular inspections, adjustments and preventative maintenance on the debris/safety boom, as well as PCA's safety boom upstream of the Norland Dam.

CLIENT

Timber Run Hydropower Corporation

LOCATION

In the village of Norland, On., on the Gull River

DATE

Sourcing, installation and commissioning: 2019 – 2020

Team

Bryan Moloughney Ing., M.Ing., PMP.

COST

30 000 $

PROFESSIONAL FEES

9 000 $

Services Provided

  • Concept preparation and validation
  • Sourcing with local suppliers
  • Managed the logistics, timing and delivery of the boom
  • Supervised the assembly and installation
  • Determined the appropriate positioning, elevation,
    anchor points and orientation
  • Commissioning and long-term support

Other tasks could include;

  • Detailed engineering and drawings
  • In-water anchors and multi-span sections

Challenges

  • Variable water level and strong currents
  • Heavy flows of pine needles and oak leaves
  • Supervising & QA/QC of the work while the Contractor
    was unfamiliar with the product

Digital Twin