Sustainability & Responsibility

left arrow

We are focusing on the UN’s #7 Sustainability Development Goal: Affordable and Clean Energy and we invite you to pledge your house to the cause.

left arrow

We support PMI’s 2022 Hours for Impact initiative where we have committed to assisting local organizations in executing their projects

Our team also volunteers to help organize events in their technical and personal circles, most recently the PMI’s 2022 Revelations Symposium.

We are always looking for additional causes to support, from river and lake cleanups to teaching and volunteer opportunities to many others.

Feel free to reach out at any time.

GHG Emissions

MNRF - Lifelines on 10 Dams around Sudbury

Description de projet

The Ministry of Natural Resources and Forestry mandated Equinox Construction Services (ECS) to fabricate and install a lifeline on the new monorail

system, on 10 different dams in the Northeast District.

The work included measuring the spacing between the posts, sourcing the lifeline components that respected the typical details, designing a clamped

connection for the removable steps and all the traveling and site work required to deliver the project to the Client’s specifications.

With these lifelines and removeable steps, the stoplog lifting and lowering operations will now be more secure and move accessible.

In fact, an important quantity of MNRF dams are receiving new monorail systems along with new lifelines in order to reduce the risks involved with the

operation of their infrastructure.

CLIENT

Ministry of Natural Resources and Forestry

LOCATION

10 different dams around Subdury, in the Northeast District

DATE

Fall 2023

Team

Bryan Moloughney P. Eng.

COST

90 000 $

PROFESSIONAL FEES

Included

Services Provided

  • Project & Construction Management tasks
  • Design of clamped connections
  • Delivery logistics and traveling to 10 remote sites
  • Responsible for the Execution of the work as well as the QA/QC requirements
  • Owner of the Project Budget and Schedule
  • Owner of the Change Management process and Communications

Challenges

  • 2024 223050 - PDS ENG - MNRF 10 Dams Sudbury - Lifelines
  • Completing the work on dams with little access for lifting equipment
  • Remote work area needed extensive planning and preparation