Sustainability & Responsibility

left arrow

We are focusing on the UN’s #7 Sustainability Development Goal: Affordable and Clean Energy and we invite you to pledge your house to the cause.

left arrow

We support PMI’s 2022 Hours for Impact initiative where we have committed to assisting local organizations in executing their projects

Our team also volunteers to help organize events in their technical and personal circles, most recently the PMI’s 2022 Revelations Symposium.

We are always looking for additional causes to support, from river and lake cleanups to teaching and volunteer opportunities to many others.

Feel free to reach out at any time.

GHG Emissions

Limoges - L'Heureux Lake Dam - Spillway Gates

Description de projet

The city of St-Colomban, via the contractor Limoges et Fils, mandated Equinox Construction Services (ECS) to manage the L'Heureux Lake dam

replacement project. ECS was responsible for managing and monitoring the execution of the project, operating closely with the contractor to ensure the

on-time and proper execution of the work. The result - with a dam consisting of 3 independent upward-opening wall gates - was a success, and the

customer is fully satisfied. ECS also took charge of quality control and assurance through full-time site supervision.

Gate sizing was a crucial element of the project. An independent company provided detailed shop drawings and sizing while Equinox coordinated all

the work, deadlines, and changes to the plans to deliver a functional, durable, and aesthetically pleasing product.

The L'Heureux Lake dam is manually operated, and the work required to open its gates is minimal and fluid,

thanks to 3 gearboxes and rails on each gate.

CLIENT

City of Saint-Colomban

LOCATION

Southeast of L'Heureux Lake, Saint- Paul side, Saint-Colomban, Quebec

DATE

Start: September 2023 End: Spring 2024

Team

COST

325 000 $

PROFESSIONAL FEES

Included

Services Provided

  • Order and installation management
  • Engineer on site at all times
  • Management of logistics and deadlines with various customers for custom-designed parts
  • Responsible for execution with contractor
  • Responsible for quality control and quality assurance
  • Responsible for communications between different stakeholders
  • Schedule and budget management related to project management.

Challenges

  • Winter temperatures hampered the curing of specialized materials.
  • The concrete level of the spillway was not exact along the entire length of the dam
  • Project carried out in close proximity to water