Durabilité et responsabilité

left arrow

Nous nous concentrons sur l'Objectif de développement durable #7 des Nations Unies : Énergie propre et abordable et nous vous invitons à engager votre maison pour la cause.

left arrow

Nous soutenons l'initiative des Heures d'impact 2022 de PMI, dans le cadre de laquelle nous nous sommes engagés à aider les organisations locales à exécuter leurs projets

Notre équipe fait également du bénévolat pour aider à organiser des événements dans leurs cercles techniques et personnels, plus récemment le Symposium des révélations 2022 du PMI.

Émissions de GES

Fourniture et installation du barrage de sécurité Markham

Projet

The City of Markham, via Brooke Restoration and AdorTECH, hired Equinox Construction Services (ECS) to carry out the assembly and installation of the

safety boom on Toogood Pond. The material was provided by AdorTECH and fully responded to the client’s requirements.

The installation was carried out with a floating work platform and a 2-Ton hoist in order to minimize the impact on the pond’s surroundings as well as

to simplify the transportation of the blocks from the shore position to the in-water anchor locations.

The safety boom was connected to a floating buoy at the peak and shoreline anchors on each end, which were fitted with galvanized plates to contain

the anchor chain.

ECS managed the supply, logistics, and delivery, as well as the installation of the new boom. The proper positioning, elevation, depth and arrangement

of the boom were determined by the client's engineering staff.

CLIENT

AdorTECH, City of Markham

EMPLACEMENT

Toogood Pond, village of Unionville (Markham), Ontario

DATE

Sourcing, installation and commissioning - spring 2024

Équipe

Bryan Moloughney P. Eng.

COÛT

35 000 $

HONORAIRES PROFESSIONNELS

Included

Services fournis

  • Managed the logistics, timing and delivery of the boom
  • Carried out the assembly and installation
  • Adjusted the work methods to suit unforeseen site conditions
  • Determined an alternative scenario moving forward

Défis

  • Pond depth was higher than expected leading to installation challenges
  • Carrying out the work while the dam, pedestrian bridge and paths were in operation.

Jumeau numérique