Statutory inspection of dam X0005453

Projet

The owner of dam X0005354 mandated Equinox Construction Services (ECS) to undertake a Statutory Inspection of the dam, including a visual analysis of all the components, including but not limited to, the piers, the spillway, the toe of the dam, the access systems the downstream reach and the upstream impoundment along with the downstream stretch.  

Following this inspection, ECS prepared a Statutory Inspection Report which included, among other aspects, a description of how the inspection was carried out, ECS' observations on annotated photographs, our recommendations with respect to the dam's current condition and status, and finally a preliminary estimate of the construction costs associated with our recommendations.

During the inspection, particular attention was given to elements such as Public Safety Around Dams, environment protection measures and the structural defects in the reinforced concrete structure.  

CLIENT

Individual dam owner

EMPLACEMENT

Lac Saguay, Québec.

DATE

Inspection carried out in August 2023 and the report was supplied during September 2023

Équipe

COÛT

N/A

HONORAIRES PROFESSIONNELS

3 500 $

Services fournis

  • Site visit at dam barrage X0005453 in Lac Saguayn
  • Carried out a visual inspection of the dam
  • Analysis of the health and status of the various components and systems of the dam
  • Prepared a Statutory Inspection Report
  • Developed a list of recommendations
  • Estimated the construction and repair costs along with a timeline
  • Attestation of the dam's current state

Défis

  • We were required to develop an attestation of the dam's condition along with our recommendations without any previous inspection records
  • The intake was well clogged which limited the precision of our recommendations